Waste-to-Energy Facility Construction

  • Client: Bridgeport RESCO
  • Location: Bridgeport, Connecticut
  • Scope: Construction
  • Total Installed Cost: $210 Million
  • Project Completed: 1988

This facility provides dependable, environmentally safe disposal of up to 2,250 tons per day of municipal solid waste from more than a dozen towns and cities in the Bridgeport area.

The project included three B&W boilers/VonRoll grate, 192,000 lb/hr of steam at 900 psig/830°F, and a 67 megawatt GE turbine generator.