Nuclear Processing Facility
- Client: Department of Energy
- Location: Oak Ridge, TN
- Scope: Construction Management, Design
- Contract Duration: 1966 - 1990
Under two consecutive delivery order type contracts, Rust Constructors performed construction management and miscellaneous design services for a three-plant complex.
Our scope of work involved areas and materials that were radioactive and/or chemically contaminated. Projects included new facilities and rehabilitation of and modifications to existing facilities, as well as a broad range of activities such as site work, large concrete pours, and sophisticated piping and instrumentation projects.
Peak employment was 2,100 workers.