Nuclear Processing Facility

  • Client: Department of Energy
  • Location: Oak Ridge, TN
  • Scope: Construction Management, Design
  • Contract Duration: 1966 - 1990

Under two consecutive delivery order type contracts, Rust Constructors performed construction management and miscellaneous design services for a three-plant complex.

Our scope of work involved areas and materials that were radioactive and/or chemically contaminated. Projects included new facilities and rehabilitation of and modifications to existing facilities, as well as a broad range of activities such as site work, large concrete pours, and sophisticated piping and instrumentation projects.

Peak employment was 2,100 workers.